Friday 27 September 2013

Gantt Chart

Gantt Chart showing the timeline for the project.
Click to enlarge

Break Down

  • Task 1 - Literature Review 01/10/13 - 05/11/13 (5 Weeks)
  • Task 2 - Technical Review 01/10/13 - 05/11/13 (5 Weeks)
  • Task 3 - Design 01/10/13 - 05/11/13 (5 Weeks)
  • Task 4 - Implementation 01/10/13 - 14/01/14 (15 Weeks)
  • Task 5 - Experiments and Testing 14/01/14 - 24/02/14 (6 Weeks)
  • Task 6 - Analysis 14/01/14 - 24/02/14(6 Weeks)
  • Task 7 - Write Up 01/10/14 - 07/04/14(28 Weeks)
  • Task 8 - Make Poster 07/04/14 - 14/04/14(1 Week)